Three of five TBMs have started driving the approach rail tunnels to the Marmaray immersed tube, which is being placed on the bed of the Bosphorus. By early May, more than 460m had been driven out of 9.8km in twin bore.
In total, four Hitachi Zosen slurry machines, each 7.89m diameter and tagged TBMs 2-5, will drive most of the twin tunnels. The first pair – TBMs 4&5 – are driving on the Asian side. By earlier this month each TBM had bored 150m and 300m, respectively.
All four slurry TBMs will eventually dock with the immersed tube, one pair closing from the Asian side and the other two from the European side. A soil mix fill will be placed at the end of the tube through which the TBMs will advance and dock into receiving sleeves. Tight survey control in placing the last element, E1, will involve working through single access shaft on the Asian side to achieve tolerances for the TBMs to dock from the European side.
There is also a single, 7.97m diameter Lovat mixed face EPBM on the scheme, working on the European side, farther back from the shore. The TBM is building the section between Yedikule and Yenikapi, and bit the ground late January for the first of the 1,835m parallel bored stretches, though it has been stopped temporarily to await decisions on a reception shaft. Geology includes, silt, clay and limestone lenses.
The five TBMs will build 7.04m i.d. twin tubes with C50 concrete segmental lining, thicknesses being either 300mm or 320mm, respectively. Segment production is underway at the dedicated factory in Gebze.
Aside from the bored drives, the project also includes 2.4km of cut and cover tunnels, at-grade structures, four new underground stations and 37 surface stations, many of which will be upgraded. In terms of station construction, at Uskudar subcontractor Bauer has been completing diaphragm walling to depths of 55m, and shaft sinking is proceeding at Sirkeci. Much of the work is turning up archeological artifacts.
The client for the third Bosphorus crossing is the general Directorate of Railways, Harbours and Airports Construction. The contractor is a JV of Taisei and Gama-Nurol with a lump sum contract if US$768M, excluding contingencies and provisions. The client’s consultant is Avrasyaconsult, a JV led by Pacific Consultants International with Parsons Brinckerhoff its subconsultant, acting as engineer and representative. PB carried out feasibility studies in 1985. Construction started 2004 for completion in 2011.
Construction of the 19m wide by 127m long crossover cavern on the Asia side of the Bosphorus rail link is well advanced