Tunnelling on the Athens metro in Greece looks set to reach new heights as a raft of contracts go out to bid whilst existing works break through.
The award of the estimated $180M "Airport" extension to line 3 was under bidding as T&TI went to press with a decision expected in late March. Four European groups are pitching for the design and build civil works contract on phase 1, a 5.1km long tunnel. Of this, 400m will be constructed by NATM, 4km by EPBM, and the remainder as cut and cover. Work includes one station at the end of the line that must be open by June 2004 for the Athens Olympics.
The bidders are: Aegek/Aktor/Seli; Avax/J&P/Eteth; Sarantopoulos/Astaldi/Wayss & Freytag; and Alpine Bau/Terna/ Zacharopoulos.
A plethora of other works for the metro extensions is also underway. Alpine Bau and Wayss & Freytag, part of the construction JV Metro Peristeri, has just begun work on an extension westwards from the Sepolia station to Agios Antonios and Thivon stations (stations not included). The $39M, 2.8km long line 2 extension includes a 2.5km long, 8.5m i.d. double track tunnel and a 258m long single track connection tunnel to the surface depot located close to Sepolia station. The first 269m of the double track tunnel and the connection tunnel will be constructed by NATM; the rest of the contract will be excavated with a Herrenknecht shielded roadheader. The drive is scheduled to begin in November.
Finally, there is the extension southwards from Dafni to Glyfada. At just over 1km long, the contract will be constructed entirely by NATM and includes two stations. The estimated $123M contract will be bid in the summer and is slated for a June 2004 opening.
Meanwhile the very last section of the original metro programme has broken through. In mid-March contractor, Olympic Metro consortium, removed the last schist diaphragm on the 9.5m diameter NATM drive between Syntagma and Monastiraki stations. The top heading will now be followed by the bench and invert. The breakthrough brings an end to the much troubled 1.3km long section that has suffered years of delays. The contractor, originally using TBMs, experienced ground collapse and construction suspension due to archeological finds. (T&TI November ’96).