Preliminary site installation and extensive portal construction has started in preparation for TBM boring of the 1.2km long, Moutier road tunnel in north west Switzerland.

The $53M construction contract was awarded in April to Swiss company Marti Tunnelbau, with Emch + Berger as consultant, by client Direction des travaux publics du Canton de Bern.

The tunnel on the A16 Transjurane between Roches and Court will have an excavation diameter of 11.7m with a finished diameter of 10.3m. A lining of TBM-erected concrete segments will be followed by a secondary concrete lining. The tunnel will be twin bore, each 1.1km long with two traffic lanes.

The first bore is set to start in September 2002. The contractor has opted for a refurbished Herrenknecht previously used on the Grauholz, Pomy and most recently Gorgier tunnels.

The tunnel overcomes a number of obstacles. It replaces an otherwise 6% slope that would have prevented a 1st class highway classification for the road. It is cheaper than buying the land over the alignment combined with road construction costs and finally preserves the environmental beauty of the area.

The project is scheduled to take four and a half years.