The project aims to replace Ca Mountain Pass and Co Ma Mountain Pass, parts of National Highway 1A that run through Dai Lanh Mountain and have dangerous bends prone to avalanches and landslides, with two tunnels.

Originally scheduled for completion in 2016, along with other parts of National Highway 1 that are also being repaired, the VND 15.6tn (USD 742.8M) project is currently one year behind.

The construction was supposed to be carried out under the Build-Operate-Transfer (BOT) and Build-Transfer (BT) models. The Deo Ca Investment Joint Stock Company was to mobilise capital to finance the project and see a return on its investment later, while the two provincial authorities and transport ministries were in charge of providing land for the worksites.

"The investor failed to do the necessary preliminary work," said Tran Xuan Sanh, head of the ministry’s Department for Management of Traffic Work Construction and Quality. "The investor has not yet finished assessments and strategies for the construction process."

The ministry is also concerned about the investor’s financial capacity as its shareholders have committed only VND 1.078tn (USD 51.3M).

Dinh Van Chuong, head of the Project Management Department of Deo Ca Investment Joint Stocks Company, blamed the delay on slow land clearance. He said that the investor had nearly completed the resettlement area for households in Phu Yen Province who had to make way for the construction.

"The province committed to handing over space for the construction next month, but that is the rainy season, so we have to postpone it until next February," he said.

However, Nguyen Tai, chairman of Dong Hoa District People’s Committee in Phu Yen Province, said that land clearance went as scheduled. He claimed the real reason for the delay was the investor’s initial design, which was problematic because the road would have run through a high voltage electrical pole.

Slow disbursement of compensation also delayed nine affected households from moving, Tai said. While compensation amounts were determined last year, the investors did not pay until this year. Other affected households complained about unfinished power and water infrastructure in resettlement areas.

Minister Thang asked local authorities and the investor to co-operate with other experienced project management units to review both project design and staffing.