The first of four drives to excavate a pair of tunnels for a new metro line extension in Munich achieved breakthrough at Leipziger station early last month after 40 days and 501m, and relaunch was anticipated early August to complete the first tube by September.

Wayss & Freytag is working in JV with Hochtief and Bauer Spezialtiefbau to build the extension to Line 3 (U3) for the city authority. The JV was awarded the contract in October 2004 and excavation of the twin 1194m long tubes using a single 7.35m diameter Herrenknecht slurry shield began in late May.

Geology along the alignment changes from gravels and sands to marls with water-bearing confined layers of sand. The TBM is fitted with a five-spoke cutterhead equipped with rippers and scrapers for the varying ground, and face support is by bentonite slurry. Cover to the tunnel ranges from 1-1.5 diameters.

The 400mm thick concrete tunnel lining consists of six segments plus a key to form 1.5m long rings. The original design was for a secondary lining but the JV’s proposed alternative of a thicker, single lining was accepted. In the first drive from Moosach station to Leipziger station the TBM erected 334 rings, and the advance rate averaged 8.4 rings per day, or 12.5m.

One of the major challenges in the contract, aside from the geology, is the logistics of works within the station boxes, which have been excavated top-down. The temporary openings in the roof slab needed for the erection and launch as well as pull-throughs and dismantling were demanding, requiring much pre-planning.

Following the first pull-through in Leipziger station, the TBM will be re-launched to bore the 693m long second leg of the first tube, erecting 462 rings en route to reach the Olympic Shopping Center station and complete the metro tunnel. The tunnel lining has a 6.3m i.d. and outside width of 7.1m.

Following an anticipated period of three months to dismantle the TBM, transport the parts back through the tunnel and reassemble them at Moosach, the JV aims to start driving the second, parallel, tunnel before the end of this year. At the end of the excavation the sacrificial shield will be left in the ground at Olympic Shopping Center.

The cost of the measurement contract for the tunnels and construction of two underground stations is approximately US$103M, which is less than half the US$247M project cost for the entire metro extension to link to the S1 line connecting with the airport. Project funding comes mostly from the federal and Bavarian state governments with a 28% share being contributed by the city.


Breakthrough achieved at Leipziger Station on Munich’s Metro extension