In late November, Lovat reported steady progress of its 6.5m diameter mixed face TBM on the Otogar-Bagcilar extension to the Istanbul Metro in Turkey.

The work is being carried out by the contractor JV of Gülermak-Dogus who acquired the mixed face EPB machine in late 2005 and subsequently refurbished and assembled it with assistance from Lovat. Lovat has also helped with supplying on-site PLC, hydraulic and electrical engineering specialists and operators.

T&TI was told the JV had completed 659 rings out of a planned 3,900 rings total. This equates to 990m of advance. The scope calls for 2,950m of twin tunnel to be excavated, for a total bored length of 5,900m. The geology is characterised as clay, silt and sands with a maximum expected EPB pressure of 5 bar.

As T&TI went to press, shift averages of 10 rings in a 12 hour period are being achieved, with mining times varying between 17 and 22 minutes.

The JV has also purchased two additional Lovat EPB machines for expanding the Istanbul metro on other legs. One TBM is in transit to site, while the other is being manufactured in Canada.