In early August, 29 workers were killed in a tunnelling accident in India. The tragedy occurred in the Himalayas as part of the works for the Tehri Hydro Development Project.

On 2 August, workers were trapped when debris fell on them whilst they were working in a shaft associated with Tunnel 3 of the scheme. Accumulated water from heavy rainfall is said to have dislodged the debris. Rescue operations got underway using excavation equipment that was already on site.

Initial reports claimed 50 men were in the tunnel when the incident occurred, resulting in 13 workers getting trapped in the tunnel. These figures were later revised to 29 fatalities.

Talking to the press, officials said the exact death toll will not be known until all of the debris is cleared, which would imply no tally system was in use for emergency situations.

An inquiry is being launched into the exact cause of the accident in the 225m deep shaft. The Indian government described a rockfall from the 695m level onto a concrete slipform below.

The slipform and workers fell through a bulkhead at the 632m level and carried on falling down to the 618m level where there were also workers present.

Some reports have suggested that if construction of the unlined section of shaft had not been delayed and had been completed before the onset of the monsoon season, then the accident would not have happened.

Five days later at least 20 workers were trapped inside a 1.5km long tunnel by flash floods and landslides in a different part of India.

They were working on the Parvathi Hydroelectric Power Project at Barshani when the incident occurred at 1.30am on Sunday 8 August. A cloudburst is said to have triggered flash floods causing landslides, which blocked the exit with silt and boulders.

Reports in the Indian press said the regional administration only learned of the situation in the early hours of the morning on the following Monday and immediately organised rescue operations.

Silt deposited by floods up to a height of 6m completely blocked the tunnel entrance. Two items of earthmoving equipment already at the site were used to clear the debris and by late Monday afternoon the Indian Ministry of Power confirmed all of the workers had been freed.