In mid-February, the Los Angeles County Metropolitan Transportation Authority (MTA) filed a reported $25 million lawsuit against the design and build team responsible for a stretch of the Pasadena Gold Line, which was completed in 2003.

T&TNA was told by an MTA spokesperson that they could confirm a lawsuit had indeed been filed on February 15 in “LA Superior Court case #BC385585”, but that no further comment would be forthcoming due to pending litigation.

Press reports said the lawsuit claimed the contractors failed to meet construction standards outlined in the contract and it cited breach of contract and negligence. Amongst others, reports said the lawsuit named Kiewit Pacific, Washington Infrastructure Services and Parsons Corporation.

T&TNA was not able to obtain a response from Parsons or Washington Infrastructure Services (part of URS Corporation by acquisition since November 2007), prior to going to press, but a spokesman for Kiewit said: “Because this matter is now in litigation, we will not be able to discuss any details publicly. We are disappointed with the current situation because we believed we had a good relationship with the Gold Line Authority, including an open and cooperative dialogue and process to address issues as they arose. This legal action has taken us by surprise. While we disagree with the premise and need for the lawsuit, we also remain committed to resolving any legitimate remaining issues with the MTA Gold Line.”

The scope of work in question was a $260 million contract that included a 1,170ft (357m) long, 30ft (9.14m) wide cut-and-cover tunnel as part of the first 13.7-mile (22km) long phase of the subway line.