The public consultation runs until 29 November 2015 and will form part of TfL’s submission for a Development Consent Order to the Government for permission to start construction. The construction is expected to begin in 2018 with the new tunnel fully operational by 2022/23.
The alignment itself cannot be changed too much however as some recently built structures anticipate a tunnel, not least a viaduct on the DLR extensions, which sets its piers wider apart at this point, and the cable car, too, which has foundations nearby.
Next steps for the project are due this summer, he says. Under the DCO process the statutory consultation can be relatively short – though about eight weeks are allocated rather than the minimum four. There was a 10-week local public consultation last year as well. An application may be submitted to the Planning Inspectorate at the beginning of next year.