After around three years of construction, the structural works for the Fehmarnbelt Tunnel portal on the German side have been completed.

Concreting work on the tunnel portal began at the German construction site in autumn 2023. A total of 450m of cut-and-cover tunnel and a 150m light transition zone have been built in the construction pit.

The approximately 600m-long section of tunnel on land was built in segments. For each segment, the base slab was concreted first, followed by the side walls and then the tunnel roof, using conventional construction methods. The final section of the tunnel roof was concreted in October 2026, completing the structural works on the tunnel portal.

A crucial element in completing the structure was the removal of the temporary retaining dyke, which formed the boundary of the construction pit for the tunnel portal. After the first 100m of cut-and-cover tunnel were completed in summer 2024, a new dyke was built above this section. Bulkheads were installed in the tunnel tubes at the seaward end to make them watertight. The area between the new dyke and the temporary retaining dyke could then be flooded and the retaining dyke removed.

In autumn 2024, the seaward section of the cut-and-cover tunnel was under water. This is where the first immersed tunnel element on the German side will be connected.

Since then, construction of the cut-and-cover tunnel continued inland from the coast. In addition to the tunnel portal, a portal building has been erected to house tunnel technical equipment, as well as ramps that will carry the road and railway into the tunnel.

The concrete for the portal was produced at an on-site concrete batching plant. Most of the materials required are delivered by cargo vessels via the Puttgarden work harbour, which has been in operation since July 2023. This avoids the need to transport materials across the island of Fehmarn by lorry.

Finishing work is now being carried out on the German tunnel portal structure, including on the openings in the light transition zone. At the same time, work inside the tunnel tubes is beginning, including installing fire protection panels on the walls.

Before the first tunnel element can be immersed on the German side and connected to the tunnel portal, further elements will be immersed on the Danish side and the tunnel trench off the German coast will be prepared.

“It is impressive to see what has been achieved here at the German construction site in just a few years. Many people from different trades have worked extremely hard to make this possible. I am very proud of what we have achieved together,” said Sund & Bælt contract director Matthias Laubenstein.

In September, the fourth tunnel element was immersed, completing nearly 900m of the 18km-long immersed tunnel. The first of the 10 special elements is also ready for immersion.