Brazilian contractor Odebrecht has claimed a record TBM advance following breakthrough of the 4.6km long Transbasin Tunnel III on the US$212M Trasvases Manabi water supply project in Ecuador.
Using a 4m diameter double shield Robbins TBM refurbished by Italian company SELI, the contractor completed boring in just 69 days.
Odebrecht started excavation on 10 March through consistent layers of muddy sandstone and sandy mudstone, with some 400m ground cover above the tunnel.
The geology was forecast from experience gained by the contractor when boring the project’s first tunnel, the 11km long Transbasin II Tunnel.
Boring of the Transbasin III Tunnel was completed on 22 May, averaging 65.9m/day. The best day’s performance was an impressive 101m, with a best week and month of 535m and 1,842m respectively.
Odebrecht construction manager Danilo Abdanur told T&TI: “With the early completion, the project is now five months ahead of schedule. The impressive achievement is a result of team effort, where workers, the owner, engineer, contractor and TBM operator have always looked for a win-win situation.”
Project manager Fernando Reis told T&TI that the success was not only down to planning between client Centre de Rehabilitation de Manabi, Brazilian designer Engevix, and SELI, but also the support of the project’s financiers, Brazilian Exim Bank and the Andean Development Corporation.
The US$390M Trasvases Manabi inter-basin project aims to provide drinking water for 70% of the population of Manabi Province and irrigate 14,000ha of land.
The scheme has three phases; La Esperanza Dam, Transbasin I Tunnel (8.3km) and Transbasin II and III tunnels (11km and 4.5km). Spanish contractor Dragados completed the Transbasin I Tunnel in 1998.