The Austrian Constitutional Court has repealed the negative decision against construction of the Semmering base tunnel. The decision comes after client Eisenbahn-Hochleistungsstrecken AG (HL-AG) lodged a complaint in July 1998 with the Austrian Constitutional Court against the provincial government of Lower Austria, which had ordered the suspension of workings at one end of the tunnel.

The suspension came as a result of political pressure exerted by Austria’s Green Party through intensive lobbying to have construction of the 21km of tunnels stopped.

However, in what is seen as a bitter twist, the Constitutional Court has granted the federal province of Lower Austria jurisdiction in environmental protection matters as far as railway projects are concerned.

This means that, before construction of the Semmering base tunnel starts, the procedure according to environmental protection laws has to be brought to a satisfactory conclusion.

This process can be time consuming; the environmental protection authority of Lower Austria has, for example, referred the whole procedure back to the beginning and ordered new expert reports on hydrogeology, fauna and flora.

Because of these circumstances, the client stopped excavation of the pilot tunnel shortly before reaching the provincial border to Lower Austria. The construction site is now clear and an automatic remote control pump for the inflow of water in the inclined pilot tunnel will be installed.

Until the environmental protection procedure has been sorted out, activities on the base tunnel will be restricted to the conclusion of this procedure and to planning the public tendering for the first two sections of the main tunnel from the portal in Gloggnitz and that in Mürzzuschlagon.