Swedish water and waste management company Va Syd has halted tunnelling procurement for its MAXIMA wastewater treatment system.
The organisation published the contract notice for the project’s wastewater tunnels and shafts in early June but has withdrawn the notice after a new risk assessment identified uncertainties over access to land.
“The decision follows our assessment, during the preparation of the environmental permit application and the work on securing utility easement, that access to land for the wastewater tunnel shafts poses a risk. This is a risk that requires us to revisit the contracting strategy. From a cost perspective, it would be too risky to proceed with the current procurement,” said MAXIMA programme director Christer Hallgren.
The processes for obtaining utility easement and the environmental permit are proceeding as planned. At the same time, work is under way to clarify the conditions and develop a plan that ensures access to land will not become an obstacle to the project.
The MAXIMA wastewater treatment system consists of several parts: a new Sjölunda wastewater treatment plant in Malmö with new outfall pipelines into the Öresund; a new large pumping station at Sjölunda; a wastewater tunnel beneath Malmö; a wastewater tunnel from Lund; and a pressurised transfer pipe from Borgeby.
The southern wastewater tunnel from Turbinen in central Malmö to Sjölunda will comprise a 5.5km-long, 5m-diameter main tunnel with two connecting 2m-diameter micro-tunnels totalling 2.4km. It will be bored at depths of 20-35m and have a storage capacity of 100,000m3.
There will be 11 shafts along the tunnel. The shaft closes to Sjölunda will have a diameter of 45m to accommodate the new pumping station, while the others will be 4-15m in diameter.
The 10km northern tunnel will connect the Källby treatment plant to the Sjölunda plant. It will also be built at depths of 20-35m. It will have a 3m internal diameter and storage capacity of 80,000m3.
There will be four shafts along the alignment. The entry shaft will have a diameter of 20m, while the others will range from 9-13m.
Tunnelling was not due to start before 2029.
MAXIMA, which has been under consideration since 2017, is designed to meet the wastewater treatment needs of the municipalities of Burlöv, Lomma, Lund, and Malmö, as well as to receive wastewater from parts of Staffanstorp and Svedala.