A Sacyr Concesiones-led consortium, with Portuguese partners ACA and DST, has been named as the preferred bidder for the Oiã-Soure section of Portugal’s Lisbon-Porto high-speed rail line.

Infraestruturas de Portugal’s €2.8bn award proposal is for the design, construction, financing and maintenance of the 60km section.

The project includes 60km of double-track, Iberian-gauge high-speed line, plus connections to the existing conventional network at Oiã, Adémia and Taveiro, adding a further 22km.

Key works include two twin-bore tunnels, 145m and 795m long; 14 bridges and viaducts, totalling 16.7km; and the upgrade of Coimbra station.

It also includes widening 16.5km of conventional line between Taveiro and the southern entrance to Coimbra B station, from double to quadruple track.

The concession will run for 30 years, with a 5.5-year construction phase followed by 24.5 years of operation.