The sixth and final TBM has been launched for the Metro Manila Subway project’s largest package.
CP101, which is being delivered by a joint venture of Shimizu Corporation, Fujita Corporation, Takenaka Civil Engineering & Construction and EEI Corporation, includes around 9.5km of 6.1m-diameter tunnels and four stations: East Valenzuela, Quirino Highway, Tandang Sora and North Avenue. The joint venture is also building a depot of 45 buildings, including maintenance and training facilities.
Four of the six TBMs have completed excavation. The fifth machine was launched on September 7, and the sixth TBM, which was recently launched from Tandang Sora, is scheduled to reach Quirino Highway Station by the end of 2027.
Works on the contract are 62% complete. Station construction is 62% complete, shield tunnelling 71% complete and building construction 27% complete.
The contract is valued at approximately ¥245bn (€1.39bn) – the largest contract awarded for a single urban railway package financed through a Japanese yen loan.
Completion of CP101 is scheduled for the end of 2030.
The Metro Manila Subway is one of the Philippines’ largest public infrastructure projects. Financed by a loan from the Japan International Cooperation Agency (JICA), the project’s total cost exceeds ¥800bn (€4.52bn). Construction began in February 2019.
Under a Japan-led framework, the project is developing a 33km underground railway connecting Mindanao Avenue in northern Metro Manila with Ninoy Aquino International Airport in the south, together with 17 stations, a depot and related facilities.
When the Shimizu-led joint venture was awarded the contract in February 2019 it reviewed the original design under an Early Contractor Involvement arrangement. Its recommendations –including replacing the NATM with shield tunnelling, simplifying station layouts and reducing the number of underground station levels – shortened the original schedule by 10 months.
The joint venture says it has continued to review the schedule, quality and safety. This has included determining priorities by areas to execute land acquisition to enable an early start to construction, revising construction plans in response to project progress, introducing interim specifications for systems such as tunnel ventilation, and deploying Japanese riggers, formwork carpenters and plasterers as instructors to establish Japanese-style quality and safety management practices.
The joint venture is supported by a multi-national team of approximately 1,300 people. To meet its contractual technology-transfer obligations, the group is increasing the number of staff sent to Japan for construction management training, to help developing engineers’ capability to work independently in the Philippines in the future.
Local employment is also a priority and around 7,000 workers currently on site are Filipino.