Geology was a mixed face with rock at the bottom of the horizon, but the rest comprising sands and gravels. Overburden was up to 5m, underneath a busy junction. The Iseki TBM was set up for a 10mm overcut.
The carrier pipe for the sewer was a 14mm-thick steel wall pipe which was installed in 6m-long sections with a complete weld at each joint. Once the carrier pipe was in place, the GRP sewer pipe was installed, again in 6m-long sections.
The machine launched from a specially designed thrust wall from a shaft that was a sheeted pit, driven to depth with a vibro hammer. A steel I-beam frame was then built and welded into pace. The same setup was used for the reception pit.
A spokesperson said, “Despite encountering some unexpected ground conditions the brand new TCS 600 Rock machine dealt extremely well with the rock, boulder and sand interface.”