TBM Berthe de Puybusque made the breakthrough at the future Ponts Jumeaux station, marking the end of its first drive.
This first section of 2.54km – out of the 4.66km of excavation planned – was marked by crossing the Fondeyre station before reaching the end of the drive at Ponts Jumeaux.
The TBM will now be returned to its starting point, the La Vache Gare – Le Grand Marché station, from where it will start its second drive towards the future Raisin station.
Eiffage and NGE-BTP are responsible for two lots on the Line C project.
Lot 1 comprises the design and construction of a 3.85km tunnel, three stations and four ancillary structures between the Colomiers auxiliary structure, located 100m from Colomiers Gare station, and the Laporte auxiliary structure. The contract also includes the construction of three shafts connecting the shafts to the tunnel.
Lot 2 covers the design and construction of civil works between the Laporte auxiliary structure and Raynal station. It includes an 8.42km tunnel, six stations, five auxiliary structures at intersections and a connecting tunnel to the maintenance site. The contract also includes the construction of nine shafts connecting the shafts to the tunnel.