Around 170,000 tonnes of excavated material for HS2’s Euston station is to be removed by rail, cutting 10,000 lorries from local roads.

HS2’s station construction partner, the Mace Dragados joint venture (MDJV), has begun the bulk excavation of the station site, digging to a depth of around seven metres, where the new HS2 platforms will be built.

HS2 is using a new loading facility beside the disused Track 17 at Euston Station and from there the material is being transported to Forders Sidings in Bedfordshire for reuse at the Stewartby Brickworks development.

Around 35,000 tonnes of excavated material was transported during trials between February and September. The trials showed that each train could carry more material than originally anticipated and that they could be operated alongside passenger services.

A further 135,000 tonnes is expected to be removed during the next phase over the coming 10 months.

Up to two trains a day, operated by GB Railfreight, will be used during the main excavation programme, with each train able to carry approximately 715 tonnes of material, equivalent to around 45 HGVs.

Each train will comprise two locomotives and up to 12 wagons. This will maximise the amount of material carried while allowing sufficient time for loading and unloading.

Track 17 is expected to remain available until early 2029.

HS2 says moving the material by rail also helps reduce the project’s carbon impact, as rail freight produces up to 76% fewer CO₂ emissions than road freight when transporting the same weight of material over the same distance.

The Euston rail freight programme is part of HS2’s wider commitment to make better use of the existing railway during construction. Freight trains transported aggregate to sites in Buckinghamshire and Birmingham, delivered tunnel segments to West Ruislip and Willesden, and carried excavated material from construction sites around Old Oak Common.

Patrick Cawley, director for on network works at Network Rail and HS2, said it had been a collaborative effort across many different teams to accommodate the freight trains alongside the day-to-day operation of one of Britain’s busiest stations.