Repair work to construct a new concrete inner ring in the Netherlands’ Westerschelde Tunnel is due to commence on January 11.

The repairs to the east tube are required after cracks developed in several concrete segments, and one segment suffered a fracture.

Installing the new concrete liner over a 30m section – effectively a tunnel within a tunnel – will take four months.

The 6.6km twin-tube tunnel in Zeeland is Europe’s longest bored road tunnel in soft soil. It has an internal diameter of 10.1m and the two tubes are connected by 26 cross-passages at 25m intervals.

The tunnel opened in 2003.

Before the new inner ring can be constructed, the tunnel must be completely cleared at the site of the repair. The fire-resistant lining, technical installations, tiled walls, concrete barriers, and the entire road surface will be removed to expose the existing tunnel structure.

The existing structure will be cleaned, and minor damage repaired. A new concrete substructure will be installed in the space previously occupied by the underlying road layers, providing a solid foundation for the new inner ring.

This will be followed by construction of the new inner ring. Prefabricated reinforcement structures will be placed inside the tunnel, and the new concrete ring cast in four sections using movable formwork.

Once the new inner ring is complete, the fire-resistant lining, road surface, barriers, tiled walls, and technical installations will be reinstalled.

“A repair of this kind has never before been carried out in an existing, operational tunnel,” said Westerscheldetunnel managing director Marco Heijdens. “We are going to install an entirely new concrete structure while working within the confined space of the existing tunnel – a massive technical challenge.”

The new inner ring will reduce the width of the road by 35cm on both sides but simulations showed this would not impact drivers.