Schiavone Lane Dragados JV has launched the second TBM on the Hudson Tunnel Project to mine the southern tube of the Palisades Tunnel. The TBM driving the northern tunnel tube was launched in October.

The two 8.7m-diameter, 152m-long machines are building the first 1.6km of the new rail tunnel tubes in New Jersey, from the tunnel portal in North Bergen to the Hudson County Access Shaft on the border of Weehawken and Hoboken.

The single shield Herrenknecht TBMs are designed for the hard, dry rock of this first section. When they reach the access shaft, they will be removed and replaced with a second pair of machines built for the mixed ground conditions under the Hudson River.

Including scheduled pauses for maintenance, it will take approximately one year to build this section of the tunnel.

Each of the TBMs will install nearly 850 rings of tunnel lining, assembled from more than 5,000 segments. To date, the machine that launched in October has bored approximately 122m of the northern tube and installed more than 60 tunnel lining rings.

Palisades
The two 8.7m-diameter, 152m-long single shield TBMs are designed for the hard, dry rock of this 1.6km section PHOTO: Gateway Development Commission (GDC)

Gateway Development Commission (GDC) commissioners said the Hudson Tunnel Project was “moving forward full steam ahead”.

“We are grateful for the many partners and supporters who have helped us reach this milestone. Every foot that these machines bore brings us closer to delivering the modern, reliable rail system our region needs,” they said in a joint statement.

The Hudson Tunnel Project is separated into 10 construction packages. The first stretch of tunnel boring and construction of the Hudson County Access Shaft are part of the Palisades Tunnel Project. Schiavone Lane Dragados JV is leading construction of this package, with the Port Authority of New York and New Jersey managing project delivery in partnership with the GDC.