Eiffage Génie Civil and NGE-BTP have recorded another breakthrough on Toulouse Metro Line C.

TBM Jeanne Marvig has arrived at the future Saint-Martin – Airbus station, marking the machine’s third breakthrough.

The milestone follows breakthroughs at Colomiers Gare and Fontaine Lumineuse and marks excavation of 3.15km of tunnel.

TBM Jeanne Marvig has completed 80% of the drive and now has less than 700m remaining to reach the final shaft at Puits Laporte. There, the machine will be dismantled and lifted out of the ground.

The Toulouse Metro Line C is a new 27km metro line in the Toulouse metropolitan area, with 21 stops, including five interconnections with railway stations.

The Eiffage-led consortium was awarded Lots 1 and 2 civil engineering contracts by Tisséo Ingénierie and has deployed three TBMs for the project.

Lot 1, which covers Line C from the Colomiers auxiliary structure, located 100m from Colomiers Gare station, to the Laporte auxiliary structure, includes the design and construction of a 3.85km tunnel, three stations and four ancillary structures between stations. It also includes the construction of three shafts connecting the shafts to the tunnel.

Lot 2 covers the section from the Laporte auxiliary structure to Raynal station. The work includes the design and construction of an 8.4km tunnel, six stations, five auxiliary structures at intersections and a connecting tunnel to the maintenance site. It also includes the construction of nine shafts.

Earlier this month, following breakthroughs at Fondeyre and Ponts-Jumeaux stations, TBM Berthe de Puybusque reached the future Lycée Toulouse-Lautrec station.